Current Activities

Genesee Avenue Traffic Shift: On January 2, 2018, crews began shifting traffic to the outer lanes of Genesee Avenue from La Jolla Village Drive to Nobel Drive. Crews also began construction on the viaduct - a bridge structure that will carry the Trolley down the middle of Genesee Avenue. This work is focused on Genesee Avenue, from Regents Road to Nobel Drive. Northbound and southbound lanes of Genesee Avenue will be restriped and shifted to the outer lanes from Regents Road to Nobel Drive while crews begin work in the median. Large drilling equipment will be set up within the median. Traffic control phasing and lane configuration may vary between day and night work hours. Traffic control signs, including necessary detours for motorists, pedestrians and bicyclists, will be posted. These types of traffic controls will be deployed at various times through the project's construction. 

Tuesday, June 21

Closures:                                                                                            

  • Lane closure on northbound Genesee Avenue from Nobel Drive to Esplanade Court from 9 p.m. to 5 a.m.

View additional information.       

Balboa Avenue: Crews continue to work nights to minimize impacts to local traffic. For all residents and businesses in the area, access to driveways will be maintained throughout the project. There may be some portions of roads closed or detoured at night. 

Completed Activities

Overnight Closure of La Jolla Village Drive: On Sunday, October 9, intermittent, overnight closures will be in place as crews stripe and install signage. 

Intermittent closures will be phased in the following order: 

  •  Southbound I-5 on-ramp from Genesee Avenue and single lanes of southbound I-5 between Genesee  Avenue and La Jolla Village Drive
  •  Southbound I-5 on-ramp from eastbound La Jolla Village Drive
  •  Southbound I-5 off-ramp to La Jolla Village Drive
  •  Both directions of La Jolla Village Drive and the southbound I-5 on-ramp from westbound La Jolla  Village Drive.

Work and closure hours will be from 9 p.m. to 5 a.m. Please use caution when traveling near the work area. 

View additional information.  

Overnight Closure of Nobel Drive: On Wednesday, Oct. 5, an overnight full closure will be in place on the Nobel Drive overcrossings as crews stripe and install signage. Additionally, access to the southbound I-5 on-ramp from eastbound Nobel Drive will be closed. Work and closure hours will be from 9 p.m. to 5 a.m. Please use caution when traveling near the work area. 

View additional information.  

Lane Closures on Santa Fe Street for Roadway Improvements: Beginning Monday, July 11 and continuing for approximately eight weeks, crews will improve and repave the roadway on Santa Fe Street between Damon Avenue and Balboa Avenue near the businesses. Daytime lane reductions will be in place at all other times; through traffic access will be maintained. Nighttime full closures will be in place from 7 p.m. to 5 a.m. Sunday through Thursday. Please follow detour routes and signage.

Pacific Highway Lane Closures: Beginning Tuesday, May 31, and continuing for approximately two months, crews will build a median barrier wall on Pacific Highway near the Old Town Transit Center. A single lane closure will be in place in both directions on Pacific Highway for 24 hours a day as crews perform this work. Through traffic access will be maintained and flaggers may be present at times to help direct traffic. Please use caution when traveling near the area. 

Lane Reduction at Cedar Street and Kettner Boulevard Intersection: Beginning Monday, June 20, and continuing through Wednesday, June 22, lane reductions will be in place at the intersection of Cedar Street and Kettner Boulevard as crews perform paving activities. Work hours are from 7 a.m. to 5 p.m. each day. Crews will minimize impacts as much as possible. Please use caution when traveling.

Lane Reduction at Cedar Street and Kettner Boulevard Intersection: Beginning Monday, May 2, and continuing through Friday, May 6, lane closures and traffic controls will be in place at the intersection of Cedar Street and Kettner Boulevard as crews install new traffic poles and signals. Work hours are from 7 a.m. to 5 p.m. each day. Crews will minimize impacts as much as possible and flaggers will be present intermittently to guide vehicles. Please use caution when traveling near the area.

View additional information.

Fez Street Parking Restrictions and Eastgate Mall Lane Closure: Beginning Wednesday, December 1, and continuing through Monday, December 6, temporary parking restrictions will be in place on eastbound Fez Street as crews restore the sidewalk area. Additionally, a single westbound lane closure will be in place on Eastgate Mall from Easter Way to Genesee Avenue, as crews construct a driveway to access the Traction Power Substation in the canyon. 

View additional information.

Santa Fe Street Traffic Shift: Beginning Tuesday, February 16 and continuing for approximately three weeks, traffic changes will be in effect on Santa Fe Street for crews to pave the Rose Creek Bikeway. Impacts will be in place between Karl Strauss Brewing Company and Jaguar Coventry Cars of San Diego. One lane will remain open at all times, and flaggers will be present to direct traffic. Driveway impacts are anticipated but access will be maintained. Work hours will be Mondays through Fridays from 7 a.m. to 5 p.m. each day. 

View additional information.

Widening of W. Morena Boulevard: UPDATE: Beginning Monday, January 18 and continuing for approximately three months, lane closures will be in place on W. Morena Boulevard. Crews will widen the boulevard and construct a pedestrian ramp that will provide access to the future Tecolote Road Trolley Station. The closures will be in place near the Tecolote Road overpass. One lane will remain open in each direction and through traffic will be maintained. Work hours will be Monday through Friday from 7 a.m. to 5 p.m., but closures will be in place 24 hours a day. Crews will minimize impacts as much as possible.

View additional information

Full Closure of Vega Street: Beginning Monday, November 30 and continuing for approximately 3 weeks, a full closure of Vega Street will be in place at the intersection of W. Morena Boulevard and continuing southwest to its terminus. During the closure, crews will demolish and reconstruct Vega Street to improve access to the future Tecolote Road Trolley Station. Construction activities will include demolition, excavation, paving, curb installation, and traffic signal modifications. Typical work hours will be Monday through Friday from 7 a.m. to 5 p.m. each day. Access to nearby businesses will be maintained.

View additional information.

Daytime Construction for Future Tecolote Road Trolley Station: Beginning Monday, April 20 and continuing for the next several weeks, daytime construction activities are scheduled near Tecolote Road and W. Morena Boulevard to improve access to the future Tecolote Road Trolley Station. Crews will be removing vegetation and preparing the embankment for construction of a pedestrian ramp that will connect Tecolote Road and W. Morena Boulevard. Work hours will be Monday through Friday from 7 a.m. to 5 p.m. Work will require the use of vegetation clearing equipment and may generate noise. Crews will minimize impacts as much as possible.

View additional information.

Morena Boulevard Lane and Sidewalk Closures between Gesner Street and Jellett Street: Starting February 19, a sidewalk closure and traffic controls will be in effect on northbound Morena Boulevard to accommodate ongoing Mid-Coast Trolley construction activities. A single lane of northbound Morena Boulevard will be closed between Gesner Street and Jellett Street, along with the sidewalk at the southeast corner of the Morena Boulevard and Ingulf Street intersection. One lane of northbound traffic will remain open on Morena Boulevard, and access to businesses will be maintained at all times. Traffic control signs will be posted for construction zone safety.

View additional information.

Underground Systems Work: Through late 2020, construction crews will continue intermittent work and testing on underground communication and electrical systems for the Mid-Coast Trolley project within the railroad right-of-way between Taylor Street in Old Town and Cedar Street in Downtown San Diego. General work hours will be Sundays through Thursdays, 9 p.m. to 5 a.m., and some day and weekend work may be required. For more information on each work location, please view the fliers below: 

    Morena Boulevard Construction Activities: Beginning May 2, northbound Morena Boulevard, from Balboa Avenue to Tecolote Road, will be reduced to one lane. Southbound Morena Boulevard is reduced to one lane of traffic in some areas. Work hours will be during the day, from 7 a.m. to 5 p.m., but closures will remain in place 24 hours a day.

    View additional information.

    Marian Bear Memorial Park: Crews have fenced off an area within the Rose Creek Channel, near the existing railroad tracks, for construction activities and staging equipment purposes. There will be no access along the Rose Creek channel between Marian Bear Memorial Park and Rose Creek open space. Users of the Marian Bear Park trail should avoid entering or passing through the construction area. Please follow direction of the posted signs.

    Parking Lot Closures for Transit Center Improvements: UPDATE: This work will continue Monday, August 16, through Wednesday, August 18. Beginning Monday, July 26, and continuing intermittently through Monday, August 9, full closures of the parking lots at the Old Town Transit Center will be in place as crews make improvements to the those lots. Improvement activities include cleaning and layout inspections, and concrete repairs and replacement. Closures will rotate intermittently throughout the different parking lots. Two parking lots may be closed at a time, but access will be maintained to the remaining lot. Crews will begin improvement activities in the north parking lot and will work their way south. Each closure will be in place for 24 hours a day. Please note that while regular work days will be Mondays through Fridays, some additional weekend work is required. Following the concrete repairs and improvements, crews will return to stripe the parking lots during non-revenue service hours.

    View additional information.

    View updated notice.

    La Jolla Village Square Surface Parking Area Closures: UPDATE: In late June, crews will begin the third of four phases in their effort to reconfigure the La Jolla Village Square surface parking area. This is a continuation of work that began on March 2, 2021 to improve access to the Nobel Drive Trolley Station parking structure as well as overall traffic flow. Construction activities will include asphalt demolition, new asphalt and concrete placement, lighting installations, striping, and landscaping. Typical work hours will be Mondays through Fridays, from 7 a.m. to 5 p.m. Work will be phased and completed in fenced-off sections of the parking area. Access to businesses, the mall entrance, the underground parking garage, and the Nobel Drive Trolley Station parking structure will be maintained at all times. Work is expected to be completed by fall 2021. In anticipation of this work, the Nobel Drive Trolley Station parking structure opened to the public on February 28, 2021, and is available for use by retail patrons. 

    View additional information

    View additional information (Phase 2).

    View additional information (Phase 3).

    Full Closures of Northbound and Southbound Morena Boulevard: Beginning Tuesday, July 6, and continuing through Thursday, July 8, full nighttime closures of northbound and southbound Morena Boulevard will be in place as crews place asphalt near the future Clairemont Drive Trolley Station. Work also will require full nighttime closures of the intersection at Ingulf Street. Work and closure hours will be from 9 p.m. to 5 a.m. each night. Detour signs will be posted. Please use caution when traveling near the work area. 

    View additional information.

    Full Closure of Southbound Morena Boulevard Ramp to Westbound Balboa Avenue: Beginning Monday, June 14, and continuing through Tuesday, July 6, a full closure of the southbound Morena Boulevard ramp to westbound Balboa Avenue will be in place as crews rebuild Americans with Disabilities Act (ADA) ramps and sidewalks for the future Balboa Avenue Transit Center. Work and closure hours will be in effect 24 hours a day. Traffic control and detour signs will be posted. Please use caution when travelling near the work area.

    View additional information

    Full Closures of Genesee Avenue: On Friday, April 16, crews will begin asphalt demolition, paving, striping, and traffic signal installations on Genesee Avenue. This work begins the final phase of roadway construction activities on Genesee Avenue for the Mid-Coast Trolley project. Work will continue for approximately four weeks and will require full closures of Genesee Avenue between Regents Road and Nobel Drive. Crews will work in sections, and the full closures will be phased. For the first two weeks, work and closure hours will be from 8 p.m. through 5 p.m. the following day, Sundays through Thursdays. Please note that the first night of work has been scheduled on a Friday to accommodate a local event. Residential and school driveway access will be maintained. Please expect noise as this work is completed and use caution when traveling near the work area. 

    View additional information

    Construction of UTC Transit Center Parking Structure: Beginning in early February and continuing through November 2021, construction activities will take place in the surface parking area of University Towne Centre, near Macy’s, as crews build a parking structure for the UTC Transit Center. Work hours will be Mondays through Fridays, from 7 a.m. to 5 p.m. each day. Please use caution when traveling near the work area.

    View additional information.

    Full Closure of Voigt Drive Bridge: Beginning Monday, October 19, a full closure of the Voigt Drive bridge will go into effect. East of the bridge, Voigt Drive will reopen to traffic. Additionally, inbound access to Scripps Health facilities via Voigt Drive will be available from the east only and outbound access will remain closed. Typical work hours will be Monday through Friday from 7 a.m. to 5 p.m. but may vary depending on the type of construction activity required. The full closure of Voigt Drive bridge is expected to be in place through April 2021. This work is part of ongoing efforts for the Voigt Drive Improvements project, which will realign Campus Point Drive permanently to provide direct access to the future Voigt Drive Trolley Station and to improve traffic flow in the area. 

    View additional information

    Lane Closures on Pacific Highway, Taylor Street, and Rosecrans Street: UPDATE: Beginning Monday, July 27, construction activities will begin at the Old Town Transit Center for transit related improvements. This is a continuation of ongoing efforts to prepare for the anticipated increase in Trolley crossings at Taylor Street upon completion of the Mid-Coast Trolley project. Work began in late February 2020 and is anticipated to continue through summer 2021. Intermittent lane closures will continue to be in place on Pacific Highway, Taylor Street, and Rosecrans Street and additional work is planned for the nearby Park & Ride. These activities will require both daytime and nighttime work. Daytime work hours will be from 7 a.m. to 5 p.m. Nighttime work hours will be from 9 p.m. to 5 a.m. Please use caution when traveling in the area and follow signage. 

    View additional information

    View additional information on work at the Old Town Transit Center

    Lane Reductions and Freeway Off-ramp Closure at Balboa Avenue: Beginning Sunday, May 9, and continuing for approximately three weeks, nighttime lane reductions will be in place on Balboa Avenue/Garnet Avenue, between Mission Bay Drive and Moraga Avenue, for crews to make improvements along the median. Additionally, nighttime full closures of the northbound I-5 off-ramp to Balboa Avenue will be in place. Work and closure hours will be Sundays through Thursdays, from 9 p.m. to 5 a.m. each night. Please use caution when traveling in the area and follow signage. 

    View additional information.

    Santa Fe Street Parking Reductions: In April, crews will begin the permanent removal of parking on the west side of Santa Fe Street, between Karl Strauss Brewing Company (5965 Santa Fe Street) and Coventry Cars of San Diego (5097 Santa Fe Street), in preparation for construction of the Rose Creek Bikeway. Portions of Santa Fe Street will be intermittently reduced to a single lane to accommodate construction. Access to businesses will be maintained. 

    View additional information

    Rose Creek Bikeway ConstructionPreliminary construction of the Rose Creek Bikeway began in January 2018. Initial work included clearing and removing vegetation in the construction area near the creek between Santa Fe Street and I-5. Major construction began in June 2018, including construction of the trail, under-crossings, and a bridge. Project completion is anticipated in spring 2020.

    View additional information.

    Gilman Drive Bike Lane Near Rose Canyon Bike Path: A portion of the bike lane on Gilman Drive, below the I-5 freeway overpass, will be intermittently closed for project construction access. Cyclists will still be able to access the Rose Canyon Bike Path. Please exercise extra caution when traveling near the work area. 

    View additional information.

    Full Closure of Northbound Campus Point Drive: Beginning June 1, a full closure of northbound Campus Point Drive will go into effect between Medical Center Drive and Genesee Avenue for crews to continue efforts to realign the roadway for the Voigt Drive Improvements Project. Southbound access on Campus Point Drive will remain open and access to the UC San Diego Medical Center will be maintained, though there may be traffic delays. Typical work hours will be Monday through Friday from 7 a.m. to 5 p.m. but may vary depending on the type of construction activity required. The closure is expected to be in place through fall 2021.

    View additional information

    Nighttime Construction along Genesee Avenue: Beginning in late May and continuing for approximately two months, crews will be performing exterior finish work on the Trolley bridge above Genesee Avenue, between Regents Road and Nobel Drive. The construction activities require nighttime closures of Genesee Avenue. Typical work hours will be Sundays through Thursdays, from 8 p.m. to 5 a.m. Please expect noise as this work is completed. The construction team is aware of residents in the area and will minimize impacts as much as possible. Please follow signage and use caution when traveling in the area.

    View additional information

    Balboa Avenue Lane Closures: Beginning Friday, April 9, and continuing for approximately two weeks, lane closures will be in place on eastbound Balboa Avenue, between the Morena Boulevard overpass to Balboa Avenue and Moraga Avenue, as crews complete bus pad improvements. 

    Additionally, MTS bus service will be temporarily relocated east of the bus stop at Balboa Avenue and Moraga Avenue from Friday, April 9, through Friday, April 23. Through access on eastbound Balboa Avenue and ramp access from Morena Boulevard will be maintained. Please follow posted signage and use caution when traveling in the area. For more information regarding the bus schedule and service impacts, please visit San Diego Metropolitan Transit System.

    View additional information.

    Lane Closures at Genesee Avenue and Nobel Drive Intersection: On Thursday, April 15, there will be overnight lane closures at the intersection of Genesee Avenue and Nobel Drive for paving work. A full closure of northbound Genesee Avenue will be in place from Nobel Drive to Esplanade Court. Additionally, full closures will be in place on eastbound and westbound Nobel Drive between Genesee Avenue and Lombard Place. Work hours will be 11:30 p.m. to 5 a.m. Residential access will be maintained at all times. Please expect noise as this work is completed and use caution when traveling near the work area. 

    View additional information

    Closure of Eastbound Nobel Drive: On Wednesday, April 14, an overnight full closure of eastbound Nobel Drive will be in place from the entrances of the Shops at La Jolla Village and La Jolla Village Square to the southbound I-5 on-ramp. Additionally, access to the southbound I-5 on-ramp from eastbound Nobel Drive will be closed. During the closures, crews will pave the roadway. Work and closure hours will be from 10 p.m. to 5 a.m. Driveway access will be maintained at all times. Please heed all traffic signs and use caution when traveling near the work area.

    View additional information

    Full Closure of La Jolla Village Drive: On Thursday, April 1, an overnight full closure will be in place on the westbound and eastbound lanes of La Jolla Village Drive, between Genesee Avenue and Costa Verde Boulevard. The closure will be in effect from 11:59 p.m. on Thursday to 5 a.m. on Friday, for SDG&E crews to perform underground electrical activities. Please use caution while traveling in the area. 

    View additional information

    Full Closure of Executive Square Driveway: Beginning Thursday, March 18 and continuing through Sunday, March 22, a full closure of the Executive Square driveway will be in place for crews to replace a cross gutter. Construction activities will include demolition and placing concrete, which will require several days to cure. Work and closure hours will be from 8 p.m. on Thursday to 5 a.m. on Monday. Access will be maintained, and signage will be in place. Please use caution when traveling in the work area. 

    View additional information

    Full Closure of Executive Square Driveway: Beginning Wednesday, March 3 at 6:30 a.m. and continuing through Monday, March 8, at 5 a.m., a full closure of the Executive Square driveway will be in place. The closure will be in effect just east of the driveway's intersection with Genesee Avenue for crews to set a staircase for the future Executive Drive Trolley Station and replace a cross gutter to help improve drainage at the intersection. Detour routes and signage will be in place for motorists. 

    View additional information.

    Construction of Nobel Drive Trolley Station Parking Structure: Construction of the Nobel Drive Trolley Station parking structure is anticipated to be completed in February 2021, and construction efforts will continue through the holiday season. Typical work hours will be Monday through Friday from 6 a.m. to 5 p.m. each day, with occasional weekend work. To accommodate retail customers during the holiday season, complimentary valet service will be available Friday, November 20, 2020 through January 15, 2021, from 10:30 a.m. to 8 p.m. daily. UPDATE: Beginning Monday, August 3 and continuing for approximately two weeks, crews will be performing utility work for the future Nobel Drive Trolley Station parking structure in the La Jolla Village Square parking area. Work hours are Sunday through Thursday, 9 p.m. to 5 a.m. each night. Access to businesses, the shop entrance, and underground parking will be maintained at all times. UPDATE: Beginning Saturday, April 25, crews will be placing concrete for construction of the future Nobel Drive Trolley Station parking structure in the La Jolla Village Square parking area. Concrete pours will continue intermittently through November 2020. Construction noise from back up alarms and concrete trucks may be present. The concrete pours will typically begin at 12:05 a.m., but work hours may vary. Access to businesses and shops will be maintained at all times. Construction of the parking structure began in January 2020 and is anticipated to continue through fall 2020. Typical work hours are Monday through Saturday from 7 a.m. to 5 p.m. Once complete, the parking structure will provide spaces for transit patrons and retail customers. 

    View additional information on the holiday construction schedule

    View additional information on the utility work

    View additional information on the concrete pours

    View additional information on construction of the parking structure.

    Full Closure of Northbound Pacific Highway: On Saturday, February 27, a full closure will be in place on northbound Pacific Highway for crews to repave the roadway. Lane closures will be in place from 6 a.m. to 6 p.m., from Kurtz Street to the intersection with Taylor Street. This work is part of ongoing improvements for the Old Town Transit Center and adjacent roadways, to prepare for an increase in Trolley crossings at Taylor Street upon completion of the Mid-Coast Trolley project. 

    View additional information

    Friars Road: In fall 2016, crews began work along Friars Road between Sea World Drive and Napa Street to build the San Diego River Bridge Double Track project in advance of construction on the Mid Coast Trolley project. Several traffic control phases involving multiple lane closures and shifts will be implemented in this area throughout the course of the project to help facilitate this work. The concrete barrier railing that has been placed on Friars Road is to support both projects and also is expected to last throughout the project duration. 

    View construction notice.

    Full Closure of Friars Road: On Tuesday, February 23, a full closure of eastbound and westbound Friars Road will be in place between Sea World Drive and Napa Street, from 8 p.m. to 5 a.m. This closure is necessary for crews to restripe the roadway as they complete the restoration process for Friars Road. Please detour via Sea World Drive, Tecolote Road, Morena Boulevard, and Napa Street. 

    View additional information. 

    Full Closure of Southbound Morena Boulevard: UPDATE: On Thursday, February 18, crews will continue to set canopies for the future Clairemont Drive Trolley Station. To accommodate this work, a full closure will be in place on southbound Morena Boulevard from Gesner Street to Ingulf Street. Work and closure hours will be from 9 p.m. to 5 a.m. This is a continuation of work that began on Tuesday, February 9. Please follow signage and use caution when traveling in the area.

    View additional information.

    Full Closures of La Jolla Village Drive: Beginning the week of Sunday, January 31 and continuing for approximately two weeks, full closures will be in place on the eastbound and westbound lanes of La Jolla Village Drive. During the closures, SDG&E crews will perform underground electrical activities. The first week of full closures will begin on the westbound lanes of La Jolla Village Drive and the following week, there will be full closures on the eastbound lanes of the roadway. Work and closure hours will be Sundays through Thursdays, from 10 p.m. to 5 a.m. each night.

    Full Closure of Friars Road: On Tuesday, January 12, a full closure of eastbound and westbound Friars Road will be in place between Sea World Drive and Napa Street, from 9 p.m. to 5 a.m. This closure is necessary for crews to perform a traffic switch in preparation for roadway restoration work. Please detour via Sea World Drive, Tecolote Road, Morena Boulevard, and Napa Street. The restoration work on Friars Road will continue through the remainder of January. One lane will remain open in each direction during this time. Additional nighttime full closures may be needed, and notice will be provided beforehand. 

    View additional information.

    Full Closure of Executive Drive: Beginning Sunday, January 17 and continuing through Tuesday, January 19, a full closure of Executive Drive will be in place east of Genesee Avenue. During the closure, crews will demolish the area and pour concrete to remove and replace a cross gutter. Work and closure hours will be from 7 p.m. on Sunday through 3 p.m. on Tuesday. Please heed all traffic signs and use caution when traveling near the work area.

    View additional information

    Full Closure of Regents Road: Beginning Sunday, December 20 and continuing through Tuesday, December 22, a full closure of Regents Road will be in place between Genesee Avenue and Health Sciences Drive. During the closure, crews will demolish the roadway and pour concrete to remove and replace a cross gutter. Work and closure hours will be from 8 p.m. on Sunday through 1 p.m. on Tuesday. Please use caution when traveling near the work area and follow signage.

    View additional information.

    Full Closures of Washington Street: On Tuesday, November 17 and Wednesday, November 18, nighttime full closures of eastbound and westbound Washington Street will be in place between Hancock Street and Frontage Road. During the closures, crews will complete work on the underground communication and electrical systems for the Trolley in addition to repaving the roadway. Work and closure hours are from 9 p.m. to 5 a.m. each night. Please use caution when traveling in the area and follow posted signage.

    View additional information.

    Partial Intersection Closure at Genesee Avenue and La Jolla Village Drive: On Monday, November 9, from 9 p.m. to 5 a.m., crews will work on the traffic signals and rewire connections at the intersection of Genesee Avenue and La Jolla Village Drive for the future Trolley. A full southbound closure on Genesee Avenue will be in place between Executive Drive and Nobel Drive, with one northbound lane open. Additionally, full westbound and eastbound closures of La Jolla Village Drive will be in place between Genesee Avenue and Regents Garden Row/Coste Verde Boulevard. There will be no westbound or eastbound access through the intersection of Genesee Avenue and La Jolla Village Drive during this time.

    View additional information

    Santa Fe Street Traffic Shift and Parking Changes: On Monday, October 19, from 9 p.m. to 5 a.m., a traffic shift will be in place on Santa Fe Street as crews restripe the roadway between Karl Strauss Brewing Company (5965 Santa Fe Street) and Coventry Cars of San Diego (5097 Santa Fe Street), to accommodate construction of the Rose Creek Bikeway. Following the traffic shift, Santa Fe Street will be in its final alignment and parking on the west side of the street will be removed permanently. Flaggers will be in place to direct motorists. Please use caution when traveling in the area and follow signage. 

    View additional information

    Closures and Traffic Shifts for Balboa Avenue Bridge Construction: On Thursday, October 15, from 10 p.m.to 5 a.m., a full closure of the northbound I-5 off-ramp to Balboa Avenue will be in place for crews to perform construction activities on the Balboa Avenue Bridge. Additionally, lane restrictions and a traffic shift will be in place on Balboa Avenue/Garnet Avenue. One lane will remain open to traffic in each direction. A single lane closure also will be in place on northbound I-5, between the Mission Bay Drive and Balboa Avenue off-ramps. Detours routes and signage will be in place. 

    View additional information

    Full Closure of Voigt Drive: A full closure of Voigt Drive is in effect between parking lot P701 and Campus Point Drive. The closure is required for the Voigt Drive Improvements Project, which will realign Voigt Drive and Campus Point Drive permanently to provide direct access to the future Voigt Drive Trolley Station and to improve traffic flow in the area. The closure began Monday, April 20 and is anticipated to continue through fall 2021. Typical work hours will be Monday through Friday from 7 a.m. to 5 p.m., though occasional nighttime and weekend work may be required. Traffic controls will be in place including temporary traffic signals, temporary wayfinding and detour signage, and roadway and sidewalk reconfigurations. UPDATE: Beginning July 6, 2020, access to and from Scripps Health facilities via Voigt Drive will be closed. Both inbound and outbound access will be closed for approximately one month while crews rebuild the driveway and adjacent roadway. Once complete, crews will restore inbound access to Scripps Health facilities from Voigt Drive. Note that access via Voigt Drive will be available from the west only. Outbound access will continue to be closed and vehicles will be redirected to Genesee Avenue. 

    View additional information.

    View additional information on the Scripps Health driveway closure.

    Closures of Southbound Genesee Avenue and the Genesee Avenue/La Jolla Village Drive Intersection: Beginning Sunday, September 27 at 6 p.m. and continuing through Tuesday, September 29 at 12 p.m., a full closure of the southbound lanes on Genesee Avenue will be in place from Executive Drive to the UTC Transit Center. Additionally, on Sunday, September 27 from 10 p.m. to 5 a.m., eastbound and westbound access at the Genesee Avenue and La Jolla Village Drive intersection will be closed. The closures are necessary for crews to widen Genesee Avenue and construct a single bus pad for the new Metropolitan Transit System bus stop located near Esplanade Court. Construction activities will include demolition work, restriping, and setting K-rail as well as installing railing and performing exterior finish work on the Trolley bridge. As work progresses, crews will reopen a single lane on southbound Genesee Avenue. Please heed all traffic signs and use caution when traveling near the work area. 

    View additional information.

    Full Closures of Genesee Avenue for Bus Pad Installations: UPDATE: Beginning Sunday, September 13 at 6 p.m. and continuing through Monday, September 14 at 2 p.m., a full closure of the northbound lanes on Genesee Avenue will be in place from La Jolla Village Drive to Executive Drive. As work progresses, crews will reopen a single lane on northbound Genesee Avenue. Please heed all traffic signs and use caution when traveling near the work area. UPDATE: Beginning Sunday, August 30 through Tuesday, September 1, and continuing Tuesday, September 8 through Thursday, September 10, full closures of southbound lanes on Genesee Avenue will be in place between Executive Drive and La Jolla Village Drive. Work and closure hours begin at 6 p.m. on the first day of the scheduled closures and will continue through 2 p.m. on the final day of the closures. As work progresses, crews will reopen a single lane on southbound Genesee Avenue. This is a continuation of efforts to install bus pads for new Metropolitan Transit System bus stops that will be located adjacent to the future Executive Drive Trolley Station. The series of intermittent full closures began on Sunday, August 23 and are expected to continue through the month of September.  

    View additional information on southbound full closures

    View additional information on northbound full closures.

    Full Closures of Rose Canyon Bike Path: Beginning Tuesday, September 8 and continuing for approximately two weeks, nighttime full closures of the Rose Canyon Bike Path will be in effect for crews to conduct landscaping work. Due to limited construction access, full closures are necessary to accommodate this work. Closure hours will be Sunday through Thursday, from 9 p.m. to 5 a.m. each night. The closures have been scheduled during nighttime hours to pose as little impact as possible to cyclists and pedestrians; shuttle service will not be provided during the scheduled work hours. 

    View additional information

    Construction of Trolley Tunnel Underpass at La Jolla Colony Drive: Starting March 3, crews began construction of the Trolley underpass at La Jolla Colony Drive. To accommodate construction, lanes on La Jolla Colony Drive will be reconfigured to provide one lane in each direction. Construction is expected to be complete by late 2019. Some full weeknight and weekend closures may be required throughout construction, during which time, there will be no access to La Jolla Colony Drive from east of the Interstate 5 on- and off-ramps to Rosenda Court.

    View additional information.

    Lane Closures on Northbound I-5: On Sunday, August 30, intermittent lane closures will be in place on northbound I-5 between the Balboa Avenue off-ramp and the Mission Bay Drive on-ramp. The closures will be in effect from 5 a.m. to 9 a.m. for SDG&E crews to install power lines for the future Balboa Avenue Trolley Station. Detours are not required for this work, but please expect approximately 15-minute traffic delays. California Highway Patrol will monitor the closures. Please use caution when travelling in the area. 

    Full Closure of Nobel Drive: On Sunday, August 30, an overnight full closure of Nobel Drive will be in place from the northbound I-5 off-ramp to the entrances of the Shops at La Jolla Village and La Jolla Village Square, as crews install new railings on the Trolley bridge above Nobel Drive. There also will be a full closure of the southbound I-5 on-ramp from Nobel Drive. The closure will be in effect from 10 p.m. to 5 a.m. Driveway access will be maintained at all times. Please heed traffic signs and use caution when traveling near the work area.

    View additional information.

    Full Closure of La Jolla Village Drive Overpass: On Wednesday, August 19, an overnight full closure of the La Jolla Village Drive overpass spanning I-5 will be in place for crews to install handrail on the Trolley bridge. The closure will be in effect on the eastbound and westbound lanes of the overpass as well as the northbound and southbound loop on-ramps from La Jolla Village Drive to I-5. Work and closure hours will be from 10 p.m. to 5 a.m. Please take alternate routes to avoid potential congestion. 

    View additional information.

    Full Closure of Friars Road: On Thursday, August 6, a full closure of eastbound and westbound Friars Road will be in place between Sea World Drive and Napa Street, from 7 p.m. to 5 a.m. This closure is necessary for crews to perform exterior finish work on the San Diego River Bridge. Please detour via Sea World Drive, Tecolote Road, Morena Boulevard, and Napa Street. 

    View additional information.

    Closures of Eastbound Nobel Drive: UPDATE: On Wednesday, August 5 and Thursday, August 6, overnight full closures of eastbound Nobel Drive will be in place from the entrances of the Shops at La Jolla Village and La Jolla Village Square to the southbound Interstate-5 (I-5) on-ramp. Additionally, access to the southbound I-5 on-ramp from eastbound Nobel Drive will be closed. Work and closure hours will be from 9 p.m. to 5 a.m. each night. Driveway access will be maintained at all times. Please heed all traffic signs and use caution when traveling near the work area. This is a continuation of work that took place Sunday, July 19 through Thursday, July 23, for crews to perform utility work for the Trolley. 

    View additional information

    Closures and Traffic Shifts for Balboa Avenue Bridge Construction: On Sunday, July 19 and Monday, July 20, crews will complete the installation of an irrigation line near the Balboa Avenue Bridge. To accommodate this work, there will be full closures of the northbound I-5 off-ramp to Balboa Avenue as well as traffic shifts on eastbound and westbound Balboa Avenue/Garnet Avenue. One lane will remain open in each direction on Balboa Avenue/Garnet Avenue at all times. Morena Boulevard and Balboa Avenue ramp restrictions also may be in place. Work and closure hours will be from 9 p.m. to 5 a.m. each night. Please follow detours and use caution when traveling in the area. 

    View additional information.

    Partial Closure of Genesee Avenue/La Jolla Village Drive Intersection: On Tuesday, June 30, from 8 p.m. to 5 a.m., there will be a partial closure of the intersection at Genesee Avenue and La Jolla Village Drive as crews pour concrete on the Trolley bridge. Additionally, there will be a full closure of the southbound lanes of Genesee Avenue and only one northbound lane will remain open to traffic, between Nobel Drive and Executive Drive. Beginning at 9 p.m., there will be full closures of westbound and eastbound La Jolla Village Drive between Genesee Avenue and Regents Garden Row/Costa Verde Boulevard. There will be no westbound or eastbound access through the Genesee Avenue and La Jolla Village Drive intersection while work is underway. Please heed all traffic signs and use caution when traveling near the work area. 

    View additional information.

    Closures of Eastbound Nobel Drive: Beginning Monday, June 1 and continuing for approximately two to three weeks, overnight full closures of eastbound Nobel Drive will be in place from the entrances of the Shops at La Jolla Village and La Jolla Village Square to the southbound I-5 on-ramp. Additionally, access to the southbound I-5 on-ramp from eastbound Nobel Drive will be closed. During the closures, crews will be performing electrical utility work to connect the Trolley. Work and closure hours will be Sundays through Thursdays, from 9 p.m. to 5 a.m. each night. Driveway access will be maintained at all times. Please heed all traffic signs and use caution when traveling near the work area.

    View additional information

    Closures of La Jolla Village Drive Overpass: On Thursday, June 11, closures of the La Jolla Village Drive overpass above I-5 will be in place for crews to perform finish work on the Trolley bridge. A full closure of westbound lanes will be effect, and lane reductions will be in place on eastbound lanes. Additionally, there will be full closures of the southbound I-5 on-ramps from westbound and eastbound La Jolla Village Drive. Work and closure hours will be from 9 p.m. to 5 a.m. Please take alternate routes to avoid potential congestion.

    View additional information

    Daytime Closures of Genesee Avenue and Nobel Drive: Beginning Monday, June 1 and continuing through Friday, June 5, full closures will be in place on northbound Genesee Avenue from Nobel Drive to Esplanade Court, as well as on eastbound and westbound Nobel Drive from Genesee Avenue to Lombard Place. As work progresses, lanes may reopen to accommodate traffic on Genesee Avenue and Nobel Drive. Work hours will be 8 a.m. to 5 p.m. each day. Please expect noise as this work is completed. Please follow signage and use caution when traveling in the area.

    View additional information

    Full Closure of Friars Road: On Thursday, May 7, from 7 p.m. to 5 a.m., a full closure of eastbound and westbound Friars Road will be in place between Sea World Drive and Napa Street for crews to remove temporary walkway supports from the San Diego River Bridge. Please detour via Sea World Drive, Tecolote Road, Morena Boulevard, and Napa Street. 

    View additional information.

    Full Closure of Nobel Drive: On Tuesday, May 5, an overnight full closure will be in place from the northbound I-5 off-ramp to the entrances of the Shops at La Jolla Village and La Jolla Village Square, for concrete work on the Trolley bridge above Nobel Drive. There also will be a full closure of the southbound I-5 on-ramp from Nobel Drive. The closure will be in effect from 8:30 p.m. to 5 a.m. each night. Driveway access will be maintained at all times. Please heed all traffic signs and use caution when traveling near the work area.

    View additional information.

    Impacts to Genesee Avenue/La Jolla Village Drive Intersection: UPDATE: On Sunday, May 3 and Monday, May 4, partial overnight closures will be in effect at the intersection of Genesee Avenue and La Jolla Village Drive for crews to continue construction of the Trolley bridge. There will be a full closure in place on the southbound lanes of Genesee Avenue and only one northbound lane will remain open to traffic, between Executive Drive and Nobel Drive. Additionally, there will be no westbound or eastbound access through the intersection. Closure hours will be from 9 p.m. to 5 a.m. each night. Please heed all traffic signs and use caution when traveling near the work area. This is a continuation of work that began Sunday, April 26.

    View additional information.

    Closures and Traffic Shifts for Balboa Avenue Bridge Construction: UPDATE: Originally scheduled to take place Sunday, April 19 through Thursday, April 23, this work has been extended and will continue on Sunday, April 26. Crews will perform exterior finish work and mount an irrigation line near the Balboa Avenue Bridge. To accommodate this work, there will be full closures of the northbound I-5 off-ramp to Balboa Avenue as well as traffic shifts on eastbound and westbound Balboa Avenue/Garnet Avenue. One lane will remain open in each direction on Balboa Avenue/Garnet Avenue at all times. Morena Boulevard and Balboa Avenue ramp restrictions also may be in place. Work and closure hours will be from 9 p.m. to 5 a.m. each night. Please follow detours and use caution when traveling in the area.  

    View additional information.

    Full Closures of Genesee Avenue: UPDATE: Rescheduled to begin Monday, April 13 through Thursday, April 16, and continuing Sunday, April 19 through Thursday, April 23, nighttime full closures of Genesee Avenue will be in effect as crews remove falsework from the Trolley bridge. There will be a full closure of southbound Genesee Avenue between La Jolla Village Drive and Nobel Drive from 8 p.m. to 5 a.m. each night. Additionally, a full closure of northbound Genesee Avenue between Nobel Drive and La Jolla Village Drive will be in place from 9 p.m. to 5 a.m. each night. Please heed all traffic signs and use caution when traveling near the work area.

    View additional information

    Closures of La Jolla Village Drive Overpass: UPDATE: Beginning Tuesday, April 14 through Thursday, April 16, and continuing Sunday, April 19, closures of the La Jolla Village Drive overpass will be in place for crews to perform finish work on the Trolley bridge. Closures will be in effect on the eastbound and westbound lanes of the La Jolla Village Drive overpass above I-5 as well as the northbound and southbound loop on-ramps to I-5 from La Jolla Village Drive. Work and closure hours will be from 10 p.m. to 5 a.m. each night. Please take alternate routes to avoid potential congestion.

    View additional information.

    Closures of Nobel Drive: Beginning Monday, April 13 and continuing through Tuesday, April 14, overnight full closures will be in place on Nobel Drive for crews to perform exterior finish work on the Trolley bridge. The closures will be in effect from the northbound I-5 off-ramp to the entrances of the Shops at La Jolla Village and La Jolla Village Square, including the southbound I-5 on-ramp from Nobel Drive. Closure hours will be from 10 p.m. to 5 a.m. each night. Driveway access will be maintained at all times. Please heed all traffic signs and use caution when traveling near the work area. UPDATE: This work completed ahead of schedule, allowing for the nighttime closure on Tuesday, April 14 to be cancelled. 

    View additional information.

    Closures of Nobel Drive: Beginning Sunday, March 29, overnight full closures will be in place for crews to perform exterior finish work on the Trolley bridge above Nobel Drive, from the northbound I-5 off-ramp to the entrances of the Shops at La Jolla Village and La Jolla Village Square. There also will be a full closure of the southbound I-5 on-ramp from Nobel Drive. The closures will be in effect Sunday, March 29 and will continue on Sunday, April 5 and Monday, April 6, from 10 p.m. to 5 a.m. each night. Driveway access will be maintained at all times. Please heed all traffic signs and use caution when traveling near the work area.

    View additional information.

    Closures and Traffic Shifts for Balboa Bridge Falsework Removal: Work to remove falsework from the Balboa Avenue Bridge will continue Monday, March 30 through Thursday, April 2. To accommodate this work, full closures of the northbound I-5 off-ramp to Balboa Avenue will be in place, as well as traffic shifts on eastbound and westbound Balboa Avenue/Garnet Avenue. One lane will remain open in each direction on Balboa Avenue/Garnet Avenue at all times. Morena Boulevard and Balboa Avenue ramp restrictions may be in place during the traffic shifts. Work and closure hours will be from 9 p.m. to 5 a.m. each night. Please follow detour routes and use caution when traveling in the area. This is a continuation of work that began on Wednesday, March 11 and was previously postponed due to inclement weather. UPDATE: This work progressed ahead of schedule and was completed on Tuesday, March 31. 

    View additional information

    Overnight Closures of I-5: This March, a series of temporary overnight full closures will be in effect on both northbound and southbound I-5 as crews remove falsework from the Trolley overcrossing south of Nobel Drive. Beginning Monday, March 2 through Thursday, March 5, overnight full closures will be in place on northbound I-5 lanes from State Route 52 to Genesee Avenue. Continuing Sunday, March 8 through Thursday, March 12, overnight full closures will be in place on southbound I-5 lanes from the I-5/I-805 Interchange to Gilman Drive/La Jolla Colony Drive. Work and closure hours will be from 9:30 p.m. to 5 a.m. each night. Additional lane reductions may be needed and advanced notice will be provided. Please follow detours and take alternate routes to avoid potential congestion. UPDATE: Falsework removal at the Trolley overcrossing south of Nobel Drive progressed ahead of schedule and the full closures of southbound I-5 were completed on Monday, March 9.

    View additional information

    Full Closure of Ocean Beach Bike Path: Beginning Monday, February 3 at 6 a.m., a temporary full closure of the Ocean Beach Bike path will go into effect between Pacific Highway and Morena Boulevard. The closure will be in place for approximately four weeks while crews replace the bike path and install a handrail. The bike path is anticipated to reopen by 6 p.m. on Friday, February 28. This work was originally scheduled to begin on Tuesday, January 21 but was postponed due to unforeseen circumstances. UPDATE: the reopening of the Ocean Beach Bike Path has been been postponed. The bike path is now scheduled to reopen by 8 a.m. on Monday, March 2. 

    View additional information.

    Train Control System Upgrade: Beginning the evening of Friday, February 21, full weekend lane reductions will be in place across the railway tracks at Taylor Street as crews upgrade the train control system from the Santa Fe Depot to the Old Town Transit Center. Work and lane reductions will be in effect from 9 a.m. on Friday, February 21 through 5 a.m. on Monday, February 24. Flaggers will be present and traffic controls will be in place. 

    View additional information

    Tecolote Road TPSS Installation: On Tuesday, February 18, a traction power substation (TPSS), which will provide power for the Trolley, will be installed at Tecolote Road, near the railroad right-of-way. Installation work will begin at 10 p.m. on Tuesday and will continue to 9 a.m. on Wednesday. Flaggers will be present on W. Morena Boulevard during this time. This work may generate noise and crews will minimize impacts as much as possible. 

    View additional information

    Full Closures of W. Morena Boulevard: Beginning Sunday, February 9 and continuing through Thursday, February 13, full nighttime closures of northbound and southbound W. Morena Boulevard will be in place from the northern junction of W. Morena Boulevard/Morena Boulevard to Vega Street. The closures are necessary to accommodate underground electrical activities. Work and closure hours will be from 9 p.m. to 5 a.m. each night. Please follow the posted detour signs and traffic controls when traveling in the work area.

    View additional information

    Closure of Friars Road: On Tuesday, February 4, a full closure of eastbound and westbound Friars Road will be in place between Sea World Drive and Napa Street, from 7 p.m. to 5 a.m. This closure is necessary to accommodate a concrete pour for the San Diego River Bridge. Please take alternate routes to avoid potential congestion. 

    View additional information

    Full Closures of Genesee Avenue: Beginning Sunday, January 26 through Thursday, January 30, and continuing Sunday, February 2 through Thursday, February 6, nighttime full closures will be in effect on both northbound and southbound Genesee Avenue, as crews form the pedestrian bridges for the future Executive Drive Trolley Station and remove falsework from the Trolley bridge. There will be a full closure of southbound Genesee Avenue between Executive Drive and La Jolla Village Drive from 9 p.m. to 5 a.m. each night. Additionally, a full closure of northbound Genesee Avenue between La Jolla Village Drive and Executive Drive will be in place from 10 p.m. to 5 a.m. each night. Please heed all traffic signs and use caution when traveling near the work area.

    View additional information.

    Overnight Closures of La Jolla Village Drive Overpass: On Tuesday, January 21 and Wednesday, January 22, overnight closures will be in place on the eastbound and westbound lanes of the La Jolla Village Drive overpass above I-5, as crews perform finish work for the Trolley bridge. Activities will include concrete placement, patchwork, and whip blasting. Both northbound and southbound loop on-ramps to I-5 from La Jolla Village Drive will also be closed. Work and closure hours will be from 10 p.m. to 5 a.m. each night. Please take alternate routes to avoid potential congestion.

    View additional information.

    Closure of La Jolla Village Drive Overpass: On Thursday, January 16, an overnight closure will be in place on the eastbound and westbound lanes of the La Jolla Village Drive overpass above I-5, as crews place concrete for the Trolley bridge. Both northbound and southbound loop on-ramps to I-5 from La Jolla Village Drive will also be closed. Work and closure hours will be from 10 p.m. to 5 a.m. Please take alternate routes to avoid potential congestion.

    View additional information

    Impacts to La Jolla Village Drive/Genesee Avenue Intersection: On Monday, January 20, traffic controls and lane closures will be in place on Genesee Avenue as crews pour concrete for the emergency walkway on the Trolley bridge above the La Jolla Village Drive and Genesee Avenue intersection. There will be a full closure in place on the southbound lanes of Genesee Avenue and only one northbound lane will remain open to traffic, between Executive Drive and Esplanade Court. There will be no westbound or eastbound access through the La Jolla Village Drive and Genesee Avenue intersection. Closure hours will be 9:30 p.m. to 5 a.m. Please heed all traffic signs and use caution when traveling near the work area.

    View additional information.

    Impacts to La Jolla Village Drive/Genesee Avenue Intersection: On Thursday, December 19, traffic controls and lane closures will be in place on Genesee Avenue as crews remove falsework from the Trolley bridge above the La Jolla Village Drive and Genesee Avenue intersection. There will be a full closure in place on the southbound lanes of Genesee Avenue and only one northbound lane will remain open to traffic, between Executive Drive and Esplanade Court. There will be no westbound or eastbound access through the La Jolla Village Drive and Genesee Avenue intersection. Closure hours will be 10 p.m. to 5 a.m. Please heed all traffic signs and use caution when traveling near the work area.

    View additional information.

    Closures of Nobel Drive: On Wednesday December 18, a full overnight closure will be in place on Nobel Drive to accommodate a concrete pour for the Trolley bridge, from the northbound I-5 off-ramp to the entrances of the Shops at La Jolla Village and La Jolla Village Square. The full closure will be in place from 10:30 p.m. to 5 a.m. During this time, there will also be a full closure of the southbound I-5 on-ramp from Nobel Drive. Driveway access will be maintained. Please heed all traffic signs and use caution when traveling near the work area.

    View additional information

    Rose Canyon Bike Path Closure: UPDATE: The previously postponed full closure of the Rose Canyon Bike Path has been rescheduled to begin on Monday, December 9, weather permitting. The closure is necessary for crews to pave the final section of the new bike path and to remove the temporary ramp currently installed near Gilman Drive. The full closure will begin at 6 a.m. on Monday, December 9 and will be in place for approximately five days. The bike path is anticipated to reopen by 6 p.m. on Friday, December 13. To accommodate cyclists, there will be bicycle-carrying shuttle service in place between the closure points from 5 a.m. to 8 p.m. each day. 

    View additional information

    Permanent Realignment of Rose Canyon Bike Path: In summer 2019, two sections of the Rose Canyon Bike Path will be relocated to the newly constructed permanent bike path. A portion of the temporary bike path that is now located on the shoulder of Interstate 5 will move to the newly constructed path by Monday, June 17. A second portion of the temporary bike path, now located along I-5 from north of Santa Fe Street to just north of SR 52, will move to the newly constructed path by Wednesday, July 3. Signs will be posted directing cyclists to the new permanent bike path. Please use caution when traveling near the work zone. 

    Closures of La Jolla Village Drive: On Wednesday, December 11, overnight closures will be in place on the eastbound and westbound lanes of the La Jolla Village Drive overpass spanning I-5 as crews pour concrete for the Trolley bridge. Both northbound and southbound loop on-ramps to I-5 from La Jolla Village Drive also will be closed. Work and closure hours will be from 10 p.m. to 5 a.m. Please take alternate routes to avoid potential congestion.

    View additional information.

    Closures of Nobel Drive: Starting December 8, full overnight closures will be in place for crews to remove falsework from the Trolley viaduct above Nobel Drive, from the northbound I-5 off-ramp to the entrances of the Shops at La Jolla Village and La Jolla Village Square. Closures will begin Sunday, December 8, and will continue through Tuesday, December 10, from 10 p.m. to 5 a.m. each night. There will also be a full closure of the southbound I-5 on-ramp from Nobel Drive, from 10 p.m. to 5 a.m. each night. Driveway access will be maintained at all times. Please heed all traffic signs and use caution when traveling near the work area.

    View additional information

    Closures of La Jolla Village Drive Overpass: On Thursday, December 5, overnight closures will be in place on the eastbound and westbound lanes of the La Jolla Village Drive overpass above Interstate 5, as crews pour concrete for the Trolley bridge. Both northbound and southbound loop on-ramps to I-5 from La Jolla Village Drive also will be closed. Work and closure hours will be from 10 p.m. to 5 a.m. Please take alternate routes to avoid potential congestion.

    View additional information

    Closures of La Jolla Village Drive Overpass: On Monday, November 25, overnight closures will be in place on the eastbound and westbound lanes of the La Jolla Village Drive overpass above I-5, as crews pour concrete for the Trolley bridge. Both northbound and southbound loop on-ramps to I-5 from La Jolla Village Drive will also be closed. Work and closure hours will be from 10 p.m. to 5 a.m. Please take alternate routes to avoid potential congestion.

    View additional information.

    Overnight Closures of I-5On Monday, November 18, a full closure of northbound I-5 lanes will be in place from SR 52 to La Jolla Village Drive, from 11 p.m. to 5 a.m. Southbound I-5, from La Jolla Village Drive to Gilman Drive/La Jolla Colony Drive, will be reduced to two lanes of traffic from 9 p.m. to 5 a.m. These closures are necessary to accommodate crews as they pour concrete for the Trolley overcrossing south of Nobel Drive. Please take alternate routes to avoid potential congestion.
    Closure of Friars RoadOn Thursday, November 14, a full closure of eastbound and westbound Friars Road will be in place from Sea World Drive to Napa Street, from 7 p.m. to 5 a.m. This closure is necessary to accommodate the removal of falsework from the San Diego River Bridge. Please take alternate routes to avoid potential congestion. 
    Impacts to Nobel Drive: Starting September 3, traffic controls and lane closures will be in place as crews perform driveway improvement construction activities along Nobel Drive, between Villa La Jolla Drive and Interstate 5. Work hours are scheduled Sunday through Thursday, from 9 p.m. to 5 a.m. Daytime work may be required. Driveway access will be maintained at all times. Please heed all traffic signs and use caution when traveling near the work area.

    View additional information.

    Closures of La Jolla Village Drive Overpass: On October 14, overnight closures will be in place on the eastbound and westbound lanes of the La Jolla Village Drive overpass above Interstate 5, as crews perform construction activities for the Trolley overcrossing. Both northbound and southbound on-ramps to I-5 from La Jolla Village Drive will also be closed. Work and closure hours will be from 10 p.m. to 5 a.m. Please take alternate routes to avoid potential congestion.

    View additional information.

    Overnight Closure of Northbound I-5 Lanes: On Tuesday, October 8, a full overnight closure of northbound Interstate 5 lanes will be in place from SR 52 to La Jolla Village Drive. The closure will be in effect from 9:30 p.m. to 5 a.m. Please take alternate routes to avoid potential congestion.

    View additional information.

    Morena Boulevard Construction Activities: On Saturday, October 5, crews will be pouring concrete for the ramps at the future Clairemont Drive Trolley station. Work hours will be from 5 a.m. to 9 a.m. Northbound and southbound Morena Boulevard will remain open. Flaggers will be present to direct trucks in to and out of the construction site. The use of concrete trucks may cause moderate noise levels. Please use caution when driving near the work area. 

    View additional information

    Olive Street TPSS Installation: Starting Monday, September 30, and continuing through Friday, October 4, crews will be pouring concrete to finalize the installation of the new traction power substation (TPSS) at Olive Street, near the railroad right-of-way. Parking restrictions, a lane closure, and a sidewalk closure will be in place on Olive Street between 7 a.m. and 3 p.m. each day. Access to businesses and residences will be maintained at all times. 

    View additional information

    Full Closures of Southbound I-5 Lanes: Beginning Tuesday, October 1, full closures of southbound I-5 lanes will be in place from the I-5/I-805 Interchange to La Jolla Colony Drive. On Tuesday, October 1, the closure will be in effect from 12 a.m. to 5 a.m. On Wednesday, October 2, the closure will begin at 9:30 p.m. and continue through 5 a.m. on Thursday, October 3. Please take alternate routes to avoid potential congestion. 

    View additional information.

    Lane Closures on Morena Boulevard: The closures originally scheduled to begin on Monday, September 16, have been postponed to the following week. Now beginning Monday, September 23, and continuing through Thursday, September 26, a full closure will be in place on southbound Morena Boulevard, between Gesner Street and Ingulf Street, from 9 p.m. to 5 a.m. each night. Crews will be pouring concrete for the platform at Clairemont Station. Please expect some noise from concrete trucks. Traffic controls will be in place. Please follow detour signs and use caution when traveling in the area.

    View additional information.

    Train Control System Upgrade: Beginning the evening of Friday, September 20, full weekend lane reductions will be in place across the railway tracks at Taylor Street as crews upgrade the train control system from the Santa Fe Depot to the Old Town Transit Center Station. Work and lane reductions will be in effect from 9 p.m. on Friday, September 20, through 5 a.m. on Monday, September 23. Flaggers will be present and traffic controls will be in place. Lane reductions will not be in place at Noell Street, as previously planned.

    View additional information.

    Train Control System Upgrade: Beginning Friday, September 6, street closures and lane reductions will be in place on Noell Street, Taylor Street, and Washington Street as crews upgrade the train control system from the Santa Fe Depot to the Old Town Transit Center Station. Overnight full closures across the railway tracks at Noell Street are scheduled from Friday, September 6, through Sunday, September 8, from 9 p.m. to 5 a.m. each night. Full weekend lane reductions across the railway tracks at Taylor Street and Washington Street are scheduled from 9 p.m. on Friday, September 6, through 5 a.m. on Monday, September 9. Flaggers will be present and traffic controls will be in place. 

    View additional information.

    Closure of Nobel Drive: Starting Wednesday night, September 4, Nobel Drive will be closed for crews to pour concrete on the Trolley viaduct, or bridge, above Nobel Drive. A full closure will be in place on Nobel Drive, from the Interstate 5 off-ramp to the entrances of the Shops at La Jolla Village and La Jolla Village Square. Closure hours begin Wednesday night, September 4 at 10 p.m., and will continue through Thursday morning, September 5 at 5 a.m. There will also be a closure of the southbound I-5 on-ramp from Nobel Drive beginning at 7 p.m. on Wednesday, September 4. Please use caution and follow detour routes when traveling in the area.

    View additional information

    Olive Street TPSS Installation: Starting Monday, August 5, crews will begin installing underground electrical conduit systems to connect and activate the traction power substation (TPSS) at Olive Street, near the railroad right-of-way. For approximately two weeks, parking restrictions will be in place on Olive Street between 7 a.m. and 5 p.m. each day, and a lane closure and sidewalk closure will be in place on Olive Street and Kettner Boulevard between 9 p.m. to 5 a.m. each night. Access to businesses and residences will be maintained at all times.

    View additional information.

    Train Control System Upgrade: Beginning Friday, August 2, street closures and lane reductions will be in place on Noell Street, Palm Street, Washington Street, and Sassafras Street as crews upgrade the train control system from the Santa Fe Depot to the Old Town Transit Center Station. Overnight full closures across the railway tracks at Noell Street and Palm Street are scheduled from Friday, August 2, through Sunday, August 4, from 9 p.m. to 5 a.m. each night. Full weekend lane reductions across the railway tracks at Washington Street and Sassafras Street are scheduled from Friday, August 2, at 9 p.m. through Monday, August 5, at 5 a.m. Flaggers will be present and traffic controls will be in place. 

    View additional information.

    Closures of La Jolla Village Drive OverpassBeginning Wednesday, July 24, closures will be in place on the eastbound and westbound lanes of the La Jolla Village Drive overpass above Interstate 5, for crews to remove falsework from the Trolley overcrossing. Both loop on-ramps to I-5 from La Jolla Village Drive will also be closed. Closures are scheduled from Wednesday, July 24, through Thursday, July 25, and will continue from Sunday, July 28, through Thursday, August 1. Work and closure hours will be from 10 p.m. to 5 a.m. each night. Please take alternate routes to avoid potential congestion.

    View additional information.

    Overnight Closures of Southbound and Northbound I-5 Lanes: Beginning Wednesday, July 17, a full overnight closure of southbound I-5 lanes will be in place from the I-5/I-805 Interchange to La Jolla Colony Drive. Additionally, beginning Thursday, July 18, a full overnight closure of northbound I-5 lanes will be in place from SR 52 to La Jolla Village Drive. Closures will be in effect from 9:30 p.m. to 5 a.m. each night. Please take alternate routes to avoid potential congestion.

    View additional information.

    Northbound I-5 Off-Ramp and Lane Closures at Balboa Avenue: A full closure of the northbound Interstate 5 off-ramp to Balboa Avenue is scheduled from midnight on Friday, July 12, to 11 a.m. on Saturday, July 13, as crews continue paving the newly widened off-ramp. During construction, one lane will be closed on eastbound Balboa Avenue/Garnet Avenue between Mission Bay Drive and Moraga Avenue. Additionally, one lane will be closed on northbound Interstate 5, between the Mission Bay Drive off-ramp and the Balboa Avenue off-ramp, from 3 a.m. to 9 a.m. on Saturday, July 13. 

    View additional information.

    Overnight Closures of Northbound I-5 Lanes: Beginning Tuesday, June 18, overnight closures will be in place on northbound Interstate 5 as crews remove falsework at Voigt Drive and install falsework south of Nobel Drive. Closures will be in effect on northbound I-5 from SR 52 to Genesee Avenue and will be scheduled from Tuesday, June 18, through Thursday, June 20, and again from Sunday, June 23, continuing to Friday, June 28, from 9:30 p.m. to 5 a.m. each night. Please take alternate routes to avoid potential congestion. Note: the northbound closures scheduled through June 28 were completed ahead of schedule on the morning of Tuesday, June 25. No further closures are scheduled for the remainder of the week.

    View additional information.

    Olive Street TPSS Installation: On Wednesday, June 26, a second traction power substation (TPSS), which will provide power for the Trolley, will be installed at Olive Street, near the railroad right-of-way. Work is scheduled from 2 a.m. to 4 p.m. Parking and lane closures will be in place on Olive Street and Kettner Boulevard during installation.

    View additional information

    Closure of Nobel Drive: Starting Tuesday night, June 11, Nobel Drive will be closed for crews to pour concrete on the Trolley viaduct, or bridge, above Nobel Drive. A full closure will be in place on Nobel Drive, from the Interstate 5 off-ramp to the entrances of the Shops at La Jolla Village and La Jolla Village Square. Closure hours begin Tuesday night, June 11, at 10 p.m. and will continue through Wednesday morning, June 12, at 5 a.m. Please use caution and follow detour routes when traveling in the area.

    View additional information.

    Overnight Closures of Southbound I-5 Lanes: Beginning Sunday, June 9, and continuing through Friday, June 28, temporary overnight closures will be in place on southbound Interstate 5 as crews remove falsework at Voigt Drive and install falsework south of Nobel Drive. Closures will be in effect on southbound I-5 from the I-5/I-805 Interchange to La Jolla Colony Drive and will be scheduled Sundays through Thursdays, from 9:30 p.m. to 5 a.m. each night. Please take alternate routes to avoid potential congestion. Additional closures on northbound I-5 will be required and notices will be provided at a later date. 

    View additional information.

    Closures of Friars Road: A full nighttime closure of Friars Road between Sea World Drive and Napa Street is scheduled from Sunday, June 9, to Thursday, June 13, to accommodate construction of the San Diego River Bridge. Work hours will be 7 p.m. to 5 a.m. each night. Traffic controls and detours will be in place for motorists. 

    View additional information.

    Closure of Nobel Drive: Starting Tuesday, May 7, at 10 p.m. and continuing through Wednesday, May 8, at 5 a.m., Nobel Drive will be closed from the I-5 off-ramp to the entrances of the Shops at La Jolla Village and La Jolla Village Square. During the closure, crews will pour concrete along the Trolley viaduct. On Tuesday, prior to the full closure, the southbound I-5 on-ramp will be reduced to one lane from 7 p.m. to 10 p.m. Please use caution and follow detour routes when traveling in the area.

    View additional information

    W. Morena Boulevard Lane Closures near Tecolote Road: On May 1 and May 2, a full, nighttime closure of northbound and southbound W. Morena Boulevard will be in effect from the northern junction of W. Morena Boulevard/Morena Boulevard to Vega Street, to accommodate utility work. Work and closure hours will be from 9 p.m. to 5 a.m. each night. Please follow the posted detour signs and traffic controls when traveling in the work area.

    View additional information.

    Closure of Morena Boulevard: On Tuesday, April 30, a nighttime full closure of northbound Morena Boulevard will be in place between Ingulf Street and Gesner Street. This closure is necessary to accommodate the delivery of a traction power substation (TPSS), which will provide power for the Trolley. Work and closure hours will be from 9 p.m. on Tuesday, April 30, through 5 a.m. on Wednesday, May 1. Please follow the posted detour signs and traffic controls when traveling near the work area.

    View additional information

    Santa Fe Street Parking Reductions: In April, crews will begin the permanent removal of parking on the west side of Santa Fe Street, between Karl Strauss Brewing Company (5965 Santa Fe Street) and Coventry Cars of San Diego (5097 Santa Fe Street), in preparation for construction of the Rose Creek Bikeway. Portions of Santa Fe Street will be intermittently reduced to a single lane to accommodate construction. Access to businesses will be maintained. 

    View additional information

    Olive Street TPSS Installation: On Wednesday, April 17, a traction power substation (TPSS), which will provide power for the Trolley, will be installed at Olive Street, near the railroad right-of-way. Work is scheduled from 2 a.m. to 4 p.m. Parking and lane closures will be in place on Olive Street and Kettner Boulevard during installation.

    View additional information

    Overnight Closure of Interstate 5 Lanes: From 9:30 p.m. on Thursday, April 11, through 5 a.m. on Friday, April 12, temporary overnight closures will continue on Interstate 5 as crews pour concrete to build the bridge deck for the Trolley overpass at Voigt Drive. There will be a full closure of southbound lanes from the I-5/I-805 Interchange to La Jolla Village Drive. Two northbound lanes will be closed from La Jolla Village Drive to Genesee Avenue. Please take alternate routes to avoid potential congestion. 

    View additional information.

    Closure of Nobel Drive: Starting early Saturday morning, March 9, Nobel Drive will be closed for crews to install falsework, the temporary structures used to support the Trolley bridge during construction. The closure will be in effect from the I-5 on-ramp to the entrances of Shops at La Jolla Village and La Jolla Village Square, and will take place from 12:01 a.m. on Saturday, March 9, through 12:01 a.m. on Sunday, March 10. Access to the shopping centers will be maintained. 

    View additional information.

    Overnight Closure of Southbound I-5 Lanes: From 9:30 p.m. on Thursday, February 28, through 5 a.m. on Friday, March 1, temporary overnight closures will continue on southbound Interstate 5 as crews pour concrete to build the bridge for the Trolley overpass at Voigt Drive. Closure will be in effect on SB I-5 from the I-5/I-805 Interchange to La Jolla Village Drive. Please take alternate routes to avoid potential congestion. UPDATE: In addition to the southbound closure, two northbound I-5 lanes will be closed from La Jolla Village Drive to Voigt Drive, also from 9 p.m. on Thursday, February 28, to 5 a.m. on Friday, March 1.

    View additional information.

    Northbound I-5 and Off-Ramp and Lane Closures at Balboa Avenue/Garnet Avenue and Grand Avenue/Garnet Avenue: As part of ongoing construction activities on the off-ramp, a full weekend closure of the I-5 off-ramp to Balboa Avenue/Garnet Avenue is scheduled from Friday, February 22, at 9 p.m. to Sunday, February 24, at 9 p.m. The off-ramp will be shifted to newly constructed pavement adjacent to the existing off-ramp.  A single lane closure of the northbound I-5 from Grand Avenue/Garnet Avenue to Balboa Avenue/Garnet Avenue will also be required from Friday, February 22, at 8 p.m. to Sunday, February 24, at 3 a.m. Additionally, motorists can anticipate nighttime closures of eastbound Balboa Avenue/Garnet Avenue on Friday, February 22, and Saturday, February 23, from 9 p.m. to 7 a.m. each night. During the nighttime closures, one lane of eastbound traffic will be shifted to westbound Balboa Avenue/Garnet Avenue. Daytime single lane closures of eastbound Balboa Avenue/Garnet Avenue will also be in place Saturday, February 23, and Sunday, February 24, from 7 a.m. to 9 p.m. each day. Motorists that require access to the off-ramp will be detoured northbound on Mission Bay Drive to Balboa Avenue/Garnet Avenue. Off-ramp and roadwork construction activities will be completed in phases and intermittent nighttime and weekend closures of the northbound I-5 off-ramp to Balboa Avenue/Garnet Avenue will continue through summer 2019.

    View additional information

    Gilman Drive Bridge: Work began in late 2016 on I-5 near Gilman Drive to prepare for construction of the Gilman Drive Bridge. Crews have installed temporary barricades near Gilman Drive that will remain for approximately two years. The new bridge will connect the west and east sides of UC San Diego and span I-5.

    View additional information.

    Intermittent Partial Closures on Genesee Avenue: This February, intermittent partial closures continue along Genesee Avenue in support of Trolley bridge construction. Girders, or large beams, will be installed on top of columns to build the viaduct, or bridge structure, that will carry the Trolley along its route. Crews have now placed girders in five different major intersections along Genesee Avenue. Though girders will continue to be set along Genesee Avenue, all required long-term closures have been completed.  

    View a time-lapse video of the girders being installed

    View additional information.

    Balboa Avenue Railroad Bridge Demolition: Work to demolish the Balboa Avenue Railroad Bridge and construct a new railroad bridge began May 17 and will continue through early 2019. Construction of a railroad bridge spanning Balboa Avenue/Garnet Avenue is ongoing. To accommodate this work, lane and ramp closures, originally scheduled through October 2018, will be in place intermittently through early 2019. Work hours will be Sundays through Thursdays, 9 p.m. to 5 a.m. One lane each of westbound and eastbound traffic on Balboa Avenue/Garnet Avenue will remain open at all times. Motorists can expect the following intermittent traffic controls: 

    • Closures of westbound and eastbound Balboa Avenue/Garnet Avenue, from Interstate 5 to Moraga Avenue.
    • Closures of north and south Morena Boulevard on- and off-ramps.
    • Closure of the Balboa Avenue/Garnet Avenue off-ramp from northbound Interstate 5.

    View additional information.

    Lane Reductions on La Jolla Village Drive: Beginning Sunday, September 9, continuing through mid- to late 2019, eastbound and westbound lanes of La Jolla Village Drive will be temporarily reduced to two lanes, between Costa Verde Blvd. and Executive Way. Crews will be erecting falsework to prepare for girder installation activities.

    Morena Boulevard Lane Closures near Tecolote Road: A nighttime closure of northbound and southbound W. Morena Boulevard, from the W. Morena Boulevard/Morena Boulevard split to Vega Street, will be in place starting the week of September 4 through early December 2018 to accommodate utility work. The closure will be in effect Sundays through Thursdays, from 9 p.m. to 5 a.m. Please follow the posted detour signs and traffic controls when traveling near the work area. 

    View additional information

    Temporary Realignment of Rose Canyon Bike Path and I-5 Impacts: Starting June 13, 2018, a southern portion of the Rose Canyon Bike Path will be temporarily relocated to the west side of the train tracks, east of Interstate 5 and north of Santa Fe Street, while crews construct a new, permanent path. The interim path will connect the north end of Santa Fe Street to about 1,000 feet north of State Route 52. A temporary realignment of the northern portion of the bike path is also in place, rerouting to a protected, temporary two-lane bikeway located on the outside shoulder of the northbound I-5 off-ramp. Sections of the permanent path will be reopened as they are completed starting in summer 2019. The full, permanent path is anticipated to open in 2020.

    View additional information.

    Gilman Drive Bridge: Work began in late 2016 on I-5 near Gilman Drive to prepare for construction of the Gilman Drive Bridge. Crews have installed temporary barricades near Gilman Drive that will remain for approximately two years. The new bridge will connect the west and east sides of UC San Diego and span I-5.

    Community Presentations

    2020

    January 22: La Jolla Village Square Tenant Meeting

    Presentation

    2019

    October 28: Pacific Beach Community Planning Group

    Presentation

    October 15: Clairemont Community Planning Group

    Presentation

    February 19: Clairemont Community Planning Group

    Presentation

    2018







    La Jolla Community Planning Association

    Presentation

    July 11: University City Planning Group

    Presentation

    May 9: Clairemont Community Planning Group – Balboa Avenue Station Specific Plan Ad Hoc Sub-Committee

    Presentation

    May 9: University City Planning Group 

    Presentation

    2017

    March 16: Irvine Company Construction Info Sessions

    Display Boards | Presentation

    2016

    November 9: University City Community Association

    Display Boards

    November 8: PS Rose Canyon 

    Presentation

    October 22: Groundbreaking Event

    Invitation | Display Boards

    September 20: Clairemont Community Planning Group

    Presentation

    August 18: Canyon Park Apartments Open House

    Display Boards

    July 26: Irvine Company Construction Info Sessions

    Display Boards | Presentation

    March 29: La Jolla Colony Open House

    Display Boards

    Stay Informed

    To stay up-to-date on the Mid-Coast Trolley project, follow us on Twitter and like us on Facebooksign-up to receive our newsletter, or contact the project team with questions at [email protected] or (877) 379-0110.

    sandaga