The I-5/Genesee Avenue Interchange project consists of five stages of construction. Work is currently underway on Stage 5. This stage of the project will take approximately 4 months to complete. The maps below include the type of work being performed in each stage. Check back regularly as construction schedules are subject to change.

I-5/Genesee Stage 2 Construction Map

Stage 2: Approximately 16 months

What to Expect:
  • Intermittent traffic delays, overnight lane closures as needed
  • Begin Genesee Avenue widening and construction on north side of the bridge
  • Construction work on retaining walls
  • Bike access will be maintained along I-5 shoulder
  • No pedestrian access within project limits
  • Begin work on bike path west of I-5

Motorists are urged to slow down during construction. Not only is it required by law, but it helps save lives. Additionally, travelers are encouraged to give themselves more time and anticipate possible traffic delays.