The I-5/Genesee Avenue Interchange project consists of five stages of construction. Work is currently underway on Stage 5. This stage of the project will take approximately 4 months to complete. The maps below include the type of work being performed in each stage. Check back regularly as construction schedules are subject to change.
Stage 1: Approximately 3 weeks
What to Expect: -
Intermittent traffic delays, but no lane closures
-
Installation of temporary concrete safety barriers (K-rail) along I-5 and on-/
off-ramps
-
Construction-related noise, dust, large equipment, and signage along I-5
-
Bike access will be maintained along I-5 shoulder
-
Access to Scripps Memorial Hospital and Science Center Drive will be
maintained throughout the
project -
Emergency responders will have access to nearby hospitals 24 hours/day,
seven days/week
Motorists are urged to slow down during construction. Not only is it required by law,
but it helps save lives. Additionally, travelers are encouraged to give themselves more
time and anticipate possible traffic delays.