Construction of Build NCC, the first package of projects being constructed as part of NCC

Program, began in 2017 and will continue through 2024. Below is a detailed list of each project’s schedule and budget. Build NCC is estimated to cost approximately $882 million with funding available from a combination of federal, state, and regional TransNet revenue sources.


Highway Projects 

Schedule:
San Elijo Lagoon Highway Bridge Replacement 
Construction Completion: 2022   

San Elijo Activity Hub Park & Ride 
Construction Completion: 2023   

Devonshire Dr. Privacy Wall 
Construction Completion: 2019   

Encinitas and Carlsbad Sound Walls 
Construction Completion: 2022   

One Carpool/High Occupancy Vehicle (HOV) lane in each direction from Manchester Ave. to Palomar Airport Rd. 
Construction Completion: 2022 

One Carpool/HOV lane in each direction from Palomar Airport Rd. to State Route 78 
Construction Completion: 2023   

Budget: $646 million

Rail Projects

Schedule: 
San Elijo Lagoon Double Track Project
Construction Completion: 2019

Chesterfield Drive Rail Crossing Improvement Project
Construction Completion: 2019

Budget: $85 million

Environmental Enhancements Projects 

Schedule:

San Elijo Lagoon Restoration
Restoration Completion: 2022 

San Dieguito Lagoon Restoration Phase II 
Restoration Completion: 2024

Budget: $167 million

Bike, Pedestrian and Community Enhancements 

Schedule:
North Coast Bike Trail (includes San Elijo Lagoon Highway Bike/Pedestrian Suspension Bridge)
Construction Completion: 2022

Santa Fe Dr. Interchange Bike/Pedestrian Upgrades
Construction Completion: 2020

Encinitas Blvd. Interchange Bike/Pedestrian Upgrades
Construction Completion: 2020 

Encinitas Coastal Rail Trail
Construction Completed: 2019

Chestnut Ave. Interchange Bike/Pedestrian Upgrades 
Construction Completion: 2024 

Palomar Airport Rd. Interchange Bike/Pedestrian Upgrades 
Construction Completion: 2024

Budget: $27 million