Construction of Build
NCC, the first package of projects being constructed as part of the 40-year
North Coast Corridor (NCC) Program, began in 2017 and will continue through 2023.
Below is a detailed list of each project’s schedule and budget. Build NCC is
estimated to cost approximately $869 million with funding available from a
combination of federal, state, and regional TransNet revenue
sources.
Highway Projects
Schedule:
San Elijo Lagoon Highway Bridge Replacement
Construction Completion: 2022
Manchester Ave. Multi-Use Facility
Construction Completion: 2022
Devonshire Dr. Privacy Wall
Construction Completed: 2019
Encinitas and Carlsbad Sound Walls
Construction Begins: 2020
One Carpool/High Occupancy Vehicle (HOV) lane in each direction from Manchester Ave. to Palomar Airport Rd.
Construction Completion: 2022
One Carpool/HOV lane in each direction from Palomar Airport Rd. to State Route 78
Construction Begins: 2021
Rail Projects
Schedule:
San Elijo Lagoon Double Track Project
Construction Completed: May 2019
Chesterfield Drive Rail Crossing Improvement Project
Construction Completion: January 2019
Environmental Enhancements Projects
Schedule:
San Elijo Lagoon Restoration
Construction Completion: 2022
Bike, Pedestrian and Community Enhancements
Projects Schedule:
North Coast Bike Trail (includes San Elijo Lagoon Highway
Bike/Pedestrian Suspension Bridge)
Construction Completion: Spring 2022
Santa Fe Dr. Interchange Bike/Pedestrian Upgrades
Construction Completion: Early 2020
Encinitas Blvd. Interchange Bike/Pedestrian Upgrades
Construction Completion: Early 2020
Encinitas Coastal Rail Trail
Construction Completed: May 2019