There are no closures scheduled from Friday evening ( 02/05 ) to Sunday
morning ( 02/07 ) along the I-15 Managed Lanes Corridor.
The Interstate 15 (I-15) Express Lanes from State Route 163 north to
State Route 56/Ted Williams Parkway will be closed this weekend starting
Sunday, at 8:00 p.m. and opening at 4:00 a.m. on Monday, ( 02/08 ).
The following closures will be in effect from Sunday evening ( 02/07 )
through Monday morning ( 02/08 ). These closures are expected to be placed
beginning at 9 p.m. and picked up by 5 a.m. or earlier Monday.
Ramps:
1. I-15 SB On ramp from WB Mira Mesa Blvd* -- K rail removal and
Striping work
2. I-15 SB On ramp from EB Mira Mesa Blvd* -- K rail removal and
Striping work
3. I-15 SB Off ramp to Carroll Canyon Rd* -- K rail removal and
Striping work
4. I-15 SB On ramp from Carroll Canyon Rd* -- K rail removal and
Striping work
5. I-15 SB Off ramp to Miramar Rd / Pomerado Rd* -- K rail removal and
Striping work
*Consecutive ramps will not be closed concurrently
Freeway Lanes:
1. I-15 NB Partial lanes from Jct SR 163 to Carroll Canyon Rd -- Bridge
work and Road work
2. I-15 SB Partial lanes from Mira Mesa Blvd to Jct SR 52 -- K
rail removal, Bridge work and Striping work
Bike Lanes:
1. The bike lane along southbound I-15 will be detoured between Centre
City Parkway and Via Rancho Parkway through the end of June 2010.
Detour signs will be posted to alert motorists and bicyclists of
the closure.
Our contractor will place signs to assist motorists through the closures.
As always, weather (rain/fog etc.) plays a role in the implementation of
planned traffic closures. Please contact me should you have any questions
or concerns associated with the closures.
Francisco Gutierrez
Construction Traffic Manager
I-15 Managed Lanes
(760) 735-5089 Office
(858) 688-1424 Cell
(760) 735-5086 Fax
|